The clock

Delays cost everyone. The clock below shows what each day of waiting costs the project. Meeting the Package is the fastest path to a yes.

$250,000

The amount of money it costs a small 100-megawatt data center for every day of delay.

  • Project Baccara

    $1.7 million lost per day of delay

    Rising while this page is open. Since you opened this page: $0.00

    $316 million lost over six months of delay

    This uses 700 megawatts at the average U.S. build cost. It does not include the chips.

  • Buckeye Tech Corridor

    $4.5 million lost per day of delay

    Rising while this page is open. Since you opened this page: $0.00

    $814 million lost over six months of delay

    This uses 1,800 megawatts, based on the $20 billion they announced. It does not include the chips.

  • Hassayampa Ranch

    $3.7 million lost per day of delay

    Rising while this page is open. Since you opened this page: $0.00

    $678 million lost over six months of delay

    This uses 1,500 megawatts at the average U.S. build cost. It does not include the chips.

  • Project Midway

    $991,000 lost per day of delay

    Megawatts: press reports.

    Rising while this page is open. Since you opened this page: $0.00

    $181 million lost over six months of delay

    This uses about 400 megawatts, from press reports. It does not include the chips.

  • Page / Huntley

    $2.5 million lost per day of delay

    Megawatts: developer stated.

    Rising while this page is open. Since you opened this page: $0.00

    $452 million lost over six months of delay

    This uses 1,000 megawatts, the 1 GW the buyer told the city it intends to permit. It does not include the chips.

The figure uses an average U.S. build cost of about $11 million a megawatt, carried at 8% a year. It does not include the chips. The source is JLL, 2026.